Example website I'll build you a website like this. apoliak.online your number here
KVADER Building contractors
your number here Quote

Galway and within 60 km

New builds, renovations and insulation

We build family homes from the foundation slab to completion, renovate apartments and houses, and insulate external walls. A fixed price and a completion date are part of the building contract.

Request a quote your number here
Price calculator by floor area KVD / KALK-01 · unit prices from our estimates
Coverage
Galway + 60 km
Site visit
within 5 working days
Itemised estimate
within 10 working days
Guarantee by type of work
24 – 60 months

Your project

150 m²
Specification
Extra work

Guide price

The calculator needs JavaScript turned on. You'll find the unit prices in the price list further down the page.

Schedule and guarantee

—

Process and guarantee

Stages signed off in writing
—
Site photo report
Once a week
Guarantee on structures
60 months
Defect report acknowledged
within 48 hours
Late completion penalty
0.05% / day

Prices exclude VAT and assume a normally accessible site and standard conditions. The exact price comes from the itemised estimate after the site visit — it's usually within 15% of the calculator.

01 — What we do

What we build

We carry out three kinds of work with our own crews. Electrics, heating and plumbing are done by regular subcontractors, coordinated by our site manager.

KVD / NOV
€520 per m², shell

New family homes

From setting out and the foundation slab through to handover for completion. We build in clay block or concrete block, to your own design or a catalogue plan.

  • Groundworks, foundation slab, damp-proof and radon barrier
  • Blockwork, floors, ring beams, stairs
  • Roof structure, roof covering, flashings
  • Windows, doors, services, plaster, floors
  • Documents for the completion certificate and the BER
Shell€520 – 700/m²
Turnkey€1,150 – 1,450/m²
Time for 150 m²11 – 13 months

Two completed new builds in our projects

KVD / REK
€620 per m² of apartment, complete

Apartment and house renovations

Complete refurbishments or single rooms. If you're living there, we can split the work into stages so you keep a working kitchen and one bathroom.

  • Demolition, removal and licensed disposal of rubble
  • New wiring, plumbing and drainage
  • Drylining, plastering, skimming, painting
  • Wall and floor tiling, floating and timber floors
  • Turnkey bathrooms, including sanitaryware
Complete apartment€620 – 860/m²
Bathroom€950 – 1,400/m²
Time for 65 m²8 – 10 weeks

Two completed renovations in our projects

KVD / FAS
€62 per m² of façade, rendered

Insulation, façades and roofs

External insulation systems for family homes and smaller apartment buildings. We calculate the insulation thickness so the building meets Part L of the Building Regulations.

  • External wall insulation with EPS or mineral wool
  • Plinth insulation with XPS
  • Insulating the ground floor soffit and the attic
  • Silicone and silicate renders in a range of colours
  • Roof renovation: covering, battens, breather membrane, leadwork
Façade, 120 mm€62 – 74/m²
Façade, 200 mm€76 – 86/m²
Roof with covering€85 – 135/m²
Time for 230 m²5 – 6 weeks

Insulation and roofing in our projects

02 — Projects

Projects with location and scope of work

Six completed jobs. Each shows the location, scope of work, area, duration and contract price excluding VAT, so you can compare it with your own project.

Showing all projects: 6

KVD / R-01
Turnkey family homeGalway – Knocknacarra, 156 m², handed over after 12 months

R-01 · Galway – Knocknacarra

156 m²

two-storey block-built house, pitched roof

Turnkey family home, Galway – Knocknacarra

  • Groundworks
  • Foundation slab
  • Walls and floors
  • Roof structure and covering
  • Insulation
  • Plaster and floors

A house built in clay block with a concrete floor and a pitched roof. Handed over with plaster, screed, floors, doors and sanitaryware fitted, ready for completion.

Floor area
156 m²
Duration
12 months
Crew on site
6 – 9 people
External walls
clay block, 380 mm
Insulation
mineral wool, 160 mm
Contract price
€196,000 excl. VAT
KVD / R-02
Shell of a family homeAthenry, 132 m², handed over after 5 months

R-02 · Athenry

132 m²

dormer bungalow

Shell of a family home, Athenry

  • Groundworks
  • Foundation slab
  • Waterproofing
  • Walls and ring beams
  • Roof structure and covering

The shell up to and including the roof: foundation slab, damp-proof and radon barrier, walls, ring beams and roof structure with concrete tiles. The owner did the finishing work themselves.

Footprint
132 m²
Duration
5 months
Crew on site
5 – 7 people
External walls
clay block, 380 mm
Roof covering
concrete tiles, 35° pitch
Contract price
€80,600 excl. VAT
KVD / R-03
Two-bed apartment renovationGalway – Doughiska, 68 m², handed over after 9 weeks

R-03 · Galway – Doughiska

68 m²

apartment block, two-bed apartment

Complete apartment renovation, Galway – Doughiska

  • Strip-out and rubble removal
  • Plumbing and wiring
  • Drylining
  • Tiling
  • Floors
  • Painting

Stripping out the bathroom core, new plumbing, drainage and wiring with its own consumer unit, a new bathroom and WC, skimming, floors and internal doors. The noisy work was done in the first three weeks.

Floor area
68 m²
Duration
9 weeks
Crew on site
3 – 5 people
Rubble removal
2 skips, 14 t
Electrics
new, certified
Contract price
€49,400 excl. VAT
KVD / R-04
Attic conversionOughterard, 92 m², handed over after 13 weeks

R-04 · Oughterard

92 m²

two bedrooms, bathroom and landing

Attic conversion to living space, Oughterard

  • Structural assessment
  • Roof windows
  • Insulation
  • Vapour barrier
  • Drylining
  • Screed and floors

A structural assessment of the roof, four triple-glazed roof windows, insulation between and under the rafters, a vapour barrier with taped joints, drylining, services and floors. The family lived in the house throughout, and the work was done from the top.

Living area
92 m²
Duration
13 weeks
Crew on site
4 – 6 people
Roof insulation
mineral wool, 300 mm
Roof windows
4, triple-glazed
Contract price
€59,200 excl. VAT
KVD / R-05
External wall insulation on a family homeOranmore, 245 m², handed over after 6 weeks

R-05 · Oranmore

245 m²

family home, two storeys, plinth

External wall insulation, Oranmore

  • Scaffolding
  • 160 mm insulation
  • Mesh reinforcement
  • Silicone render
  • Plinth
  • Sills and flashings

An external insulation system with mineral wool and silicone render, including plinth insulation, new sills and flashings. We checked the finished façade with a thermal camera and handed over the survey with the job.

Façade area
245 m²
Duration
6 weeks
Crew on site
4 – 6 people
Insulation thickness
160 mm
Heat loss
U ≈ 0.15 W/m²K
Contract price
€18,200 excl. VAT
KVD / R-06
Roof renovationTuam, 180 m², handed over after 5 weeks

R-06 · Tuam

180 m²

pitched roof, 38°

Roof renovation, Tuam

  • Stripping the roof
  • Roof structure repairs
  • Breather membrane
  • Battens
  • Clay tiles
  • Gutters and downpipes

Stripping the old covering and battens, replacing two damaged rafters, a breather membrane, new battens, clay tiles and new gutters and downpipes in coated steel.

Roof area
180 m²
Duration
5 weeks
Crew on site
4 – 5 people
Roof covering
clay tiles, 38° pitch
Rafters replaced
2
Contract price
€19,900 excl. VAT

How to check a reference

At the site visit you'll get the phone numbers of two clients we've done the same kind of work for. You call them directly, without us.

Visiting a live site

By arrangement, we'll take you to a site that's under way. You'll see how tidy the site is, the materials going in and the site diary. We arrange a time by phone.

03 — How a job runs

From site visit to handover

Eight steps every job goes through, each with the time within which we'll have it done.

01

Enquiry and phone call

We find out the type of project, the area, the location and the timescale you have in mind, and tell you straight away whether it fits our capacity.

within 24 hours
02

Site visit

We come to the site or the apartment, measure what's there, record the critical points and go through what you need.

within 5 working days
03

Estimate and schedule

You get an itemised estimate with quantities, material and labour prices, and a timetable split into stages.

within 10 working days
04

Building contract

The contract sets out a fixed price, the completion date, a late completion penalty and how any variations are handled.

1 – 2 days
05

Site set-up

Site facilities, temporary services, a skip for rubble, protection of surrounding areas and the first entry in the site diary.

2 – 4 days
06

Building in stages

Each stage has its own date and sign-off record. Once a week you get a photo report and an update on the budget spent.

per schedule
07

Snagging

Before handover we go through the work with you, make a snag list and fix everything on it.

5 – 10 days
08

Handover and guarantee

A handover record, test certificates, material guarantees and a service contact for the guarantee period.

on the day of handover
04 — Timescales

Build schedule

Typical phase durations for our three most common projects. You get the same breakdown in your estimate, with exact dates.

Phase durations by type of project
Phase Turnkey house, 156 m² Apartment renovation, 68 m² External insulation, 245 m²
Site set-up and scaffolding2 weeks3 days4 days
Groundworks and demolition3 weeks2 weeks—
Shell, floors, ring beams12 weeks——
Roof structure, covering, flashings5 weeks——
Electrics, plumbing, heating4 weeks2 weeks—
Windows and external doors1 week3 days—
Insulation and render5 weeks—4 weeks
Plaster, skim, screed6 weeks2 weeks—
Tiling and floors5 weeks2 weeks—
Sanitaryware, doors, painting3 weeks1 week—
Snagging and handover2 weeks1 week1 week
Total time, with phases overlapping 11 – 13 months 8 – 10 weeks 5 – 6 weeks

Why the rows don't add up

The phases partly overlap — while the roofer is working on the roof, the services are already going in inside. So the total row shows the real duration, including the overlap and a margin for weather.

Seasonal limits

We pour concrete down to −3 °C with an admixture, and stop below that. We apply render between +5 and +30 °C, and never in direct sun.

Drying and curing times

Cement screed dries at about 1 cm a week, anhydrite faster. We only lay floors after measuring the residual moisture, even if it means a week's delay.

When we can start

We usually have capacity 6 to 10 weeks ahead. Smaller jobs of up to 3 weeks can sometimes start sooner, if a crew is free between two stages.

05 — Build-ups and materials

The materials we use

We choose materials to suit the project and the budget. Every item in the estimate is named, with its thickness, size and unit price, so you know what's going into your build.

380 mm External walls

Walls

Clay blocks for external walls, and calcium silicate blocks where sound insulation is needed between apartments and rooms.

external 380 mm · partitions 115 / 175 mm

200 mm Façade insulation

Thermal insulation

EPS for most façades, and mineral wool on timber frames and wherever non-combustibility is required.

façade 120 – 200 mm · roof 300 mm

15 – 45° Roof pitch

Roofs and flashings

Concrete or clay tiles on pitched roofs, and coated steel for gutters, downpipes and flashings.

40/60 mm battens · breather membrane

0.75 Window Uw, W/m²K

Windows and doors

uPVC and alu-clad timber windows with triple glazing, and front doors with a thermal break.

Uw 0.75 – 0.95 W/m²K · 6 chambers

2 layers Below-ground protection

Waterproofing

Bituminous membranes against damp and radon, and liquid waterproofing under tiles in bathrooms.

2 membrane layers · 2 coats of liquid membrane

65 mm Screed thickness

Floors and finishes

Anhydrite and cement screeds, vinyl and laminate floors, large-format tiles, gypsum skim coats.

screed 50 – 65 mm · skim 2 – 3 mm

06 — Guarantee and defects

Guarantees, deadlines and defects

The guarantee is set out in the building contract and runs from the day of handover. Materials also carry the manufacturer's guarantee, and we hand over the guarantee documents in print.

Guarantee periods by type of work
Type of workGuaranteeDefect inspection within
Shell and structure60 months5 days
Roofs and flashings60 monthswithin 48 hours
Insulation and render60 months5 days
Waterproofing and bathrooms60 monthswithin 48 hours
Plaster, skim, painting24 months7 days
Floors and tiling36 months7 days
Supplied materials and equipmentper manufacturer7 days

How the timescales work

We count the completion date in the contract in working days, and it already includes a margin for normal weather. If we delay the job through our own fault, we pay a penalty of 0.05% of the contract price for every day of delay.

What extends the timescale

Frost below −5 °C for wet trades, changes to the brief during the build, waiting for a planning decision, or waiting for materials you chose to supply yourself. We record every such delay in the site diary.

Reporting a defect under guarantee

Report a defect by phone on your number here or through the form on this page. We always acknowledge it within 48 hours, and inspect within the time shown for that type of work in the table. We fix ordinary defects within 15 working days, and come straight away for anything that stops you using the building.

07 — Unit prices

Price list

Prices are for labour only, without materials, unless stated otherwise. They exclude VAT and apply to jobs within 60 km of Galway.

Blockwork, concrete and demolition
LabourUnitPriceNote
Laying 380 mm external wallsm²€26 – 32excluding blocks and mortar
Laying 115 mm partition wallsm²€17 – 21excluding materials
Foundation slab including reinforcementm²€78 – 96including materials and concrete
Machine-applied internal plasterm²€11 – 14excluding plaster mix
Demolishing partitions up to 150 mmm²€14 – 19excluding rubble removal
Rubble removal and disposal7 m³ skip€210 – 280including landfill charges
Insulation, roofing and finishes
LabourUnitPriceNote
External wall insulation including renderm²€62 – 86including materials, depending on thickness
Insulating the ground floor soffitm²€28 – 36including materials
Scaffoldingm² / month€4.20 – 5.60including delivery and erection
Pitched roof coveringm²€22 – 30excluding tiles and battens
Plasterboard ceilingm²€24 – 31including studs and boards
Wall and floor tiles up to 60 × 60 cmm²€27 – 38excluding tiles and adhesive
Skim coat and paintingm²€13 – 18including materials, two coats
Hourly rates and travel
ItemUnitPriceNote
Bricklayer, tiler, drylinerhour€32small jobs outside the estimate
General operativehour€22preparation and clean-up
Site manager, technical supervisionhour€38also on other companies' jobs
Site visit and quotejob€0within 60 km of Galway
Travel beyond 60 kmkm€0.95one trip a day is charged

Site visit within 5 days, estimate within 10

Tell us the area and type of work, and we'll arrange a site visit. Within 60 km of Galway, the site visit and itemised estimate cost €0. We reply to enquiries within 24 hours.

Request a quote your number here

Office: Monday — Thursday 7:30 — 16:00, Friday 7:30 — 14:00. Site visits 7:00 — 18:00.

08 — Instalments

Payments tied to stages

You don't pay for the whole build up front. Each instalment is tied to a completed stage, which you sign off in the site diary.

  1. Materials deposit Due when you sign the contract. We use it to buy the materials for the first stage. 15%
  2. After the shell or strip-out Once the first stage is signed off in the site diary. 25%
  3. After the services and the roof When the building is weathertight and the services are ready for testing. 25%
  4. After the finishing work After plastering, floors and fitting the sanitaryware. 25%
  5. Retention Due 30 days after handover, once every recorded snag has been fixed. 10%

Payment methods

By bank transfer against an invoice with 14-day terms; we issue a deposit invoice when you sign the contract. We accept cash payments up to €300, always with a receipt. We don't offer card payments or finance.

What the price includes

Crew labour, site overheads, travel within 60 km, site facilities and a clean-up when we finish. Materials are a separate line in the estimate, with the unit price shown.

Insurance

We hold public liability insurance for our work. The policy number is in the building contract.

09 — Contract terms

Contract, variations and cancellation

The building contract you sign has the same wording. We publish it in advance so you know the terms before the site visit.

Cancellation terms if you withdraw from the contract
When you withdrawWhat you get backWhat we charge
Within 7 days of signing, materials not yet orderedthe whole deposit€0
After materials are ordered, work not yet startedthe deposit less the materials orderedmaterials and delivery, per receipts
After work has startedthe balance of the deposit after the final accountwork actually done and materials on site
Moving the start at your request by more than 30 daysthe deposit stays in place€0
Withdrawal on our sidethe whole deposit within 14 days€0

Variations during the build

Every change from the estimate has its own variation order, with the price and the effect on the timescale. We don't start anything or invoice anything without your signature on the variation order.

Omitted work

If you drop an item from the estimate, we deduct it in full, including materials. Omissions go on the same variation order as additions.

Hidden defects found during strip-out

A rotten joist, a cracked lintel or aluminium wiring can't be seen in advance. We stop work, record what we've found and propose a solution with a price. We only carry on once you agree.

Withdrawal on our side

We can only withdraw if the information provided was untrue, if we're kept off the site for more than 30 days, or if a payment is more than 30 days late. In that case we refund the deposit within 14 days.

10 — Checks and documents

Inspection points and handover documents

An inspection point is where work is checked before it's covered up. The record and photo from each point are part of the documents you get at handover.

Inspection points during the build
Inspection pointWhat's measuredCriterion
Foundation slablevel and dimensions±5 mm / 2 m
Walls and lintelsplumb walls, lintel bearing±5 mm / storey
Plumbing and heatingpressure test before covering up6 bar, 60 min
Electricscompletion testSafe Electric certificate
Screed before flooringresidual moisture, CM methodup to 2.0%
Bathroom waterproofingcontinuous coating, including corners2 coats, corner tape
Façade after insulationthermal bridges, thermal camerano linear thermal bridges
  • 01Site diaryDaily entries: weather, headcount on site, stoppages.
  • 02Stage sign-off recordsA signed record for every completed stage and instalment.
  • 03Electrical completion certificateIssued by a Safe Electric registered contractor.
  • 04Pressure test recordWater and heating, carried out before the pipes are covered.
  • 05Material guaranteesRoofing, windows, insulation, sanitaryware and floors, in print.
  • 06Declarations of performanceDocuments for the construction products built in.
  • 07Photos of covered-up workServices in the walls and floors before they're concreted over.
  • 08Completion documentsAn as-built survey and the information for the BER.
11 — People and equipment

Who's on site and what we work with

Blockwork, façades, tiling and drylining are done by our own crews. Every job has one site manager, and you get their phone number when you sign the contract.

Site managerKeeps the site diary, coordinates crews and subcontractors, and signs off stages with the client.
Bricklaying foremanResponsible for blockwork, concrete, plastering and sticking to the quantities in the estimate.
Quantity surveyorPrepares the itemised estimate, tracks spending and prepares variation orders.
Tiler and floor layerWall and floor tiling, screeds and final floors, including bathroom waterproofing.
DrylinerCeilings, lining walls, acoustic and fire-rated systems.
Roofer and leadworkerRoofs, gutters, downpipes, flashings and roof windows.
Façade crewInsulation, scaffolding, mesh and final render, including colour.
Regular subcontractorsElectrics, plumbing and heating, always registered and certified.
KVD / CREW
The bricklaying crew on site R-01The site manager, foreman and five bricklayers pouring the ring beam.
  • 2.5 t mini digger Digging foundations, service trenches and drains, even on tight sites.
  • 200 kg builder's hoist Lifting materials to upper floors without carrying them up the stairs.
  • Silo and plastering machine Machine-applied plaster at an even thickness, with no unnecessary waste.
  • 400 m² frame scaffolding Our own scaffolding, so there's no waiting for hire and no paying for downtime.
  • Rotating laser and level Checking ceilings, screeds and window positions are level.
  • Moisture meter and thermal camera Checking screeds have dried and finding thermal bridges after insulation.
12 — Careers

Vacancies

We hire for sites within 60 km of Galway. You're home every evening, and we drive to site in a company van from a pick-up point by the office.

Bricklayer

Full-time · start straight away

Laying external and partition walls, formwork and pouring ring beams, setting lintels. You'll need at least 3 years' experience and your own hand tools.

€22 – 28an hour

Tiler

Full-time or self-employed

Wall and floor tiling, including large formats, liquid waterproofing in bathrooms and silicone joints. We're looking for someone who checks their own falls and levels.

€22 – 27an hour

Site manager

Full-time · 2 sites at a time

Keeping the site diary, coordinating crews and subcontractors, signing off stages with the client and tracking the budget. A construction management qualification is an advantage, not a requirement.

€55,000 – 70,000a year

General operative

Full-time · no experience needed

Preparing materials, running the mixer, keeping the site tidy, helping the bricklaying and façade crews. We'll train you, and after a year you can move up to bricklaying.

€15 – 17an hour

What we offer

Paid weekly, with no wages held back. We provide work clothes, boots and PPE. Power tools are company-owned, including servicing.

How to apply

Fill in the form in the Contact section, with the job and your years of experience in the description. We'll get back to you within 3 working days and arrange to meet on one of our sites.

Apply through the form

13 — Finding us

How to get here and where to park

The office is on the corner of Mason Street and Brick Lane in Galway. We sign estimates and contracts here, and do site visits at your place.

KVADER office P MASON STREET BRICK LANE city centre, 1.2 km

The office entrance is on Mason Street, just round the corner from the junction with Brick Lane. Behind the building is our yard with the store and equipment, which is closed to clients — we deliver materials straight to site.

KVD / OFFICE
26 Mason Street, GalwayEntrance on Mason Street, reserved parking outside.

Parking

There are 6 reserved visitor spaces outside the building, free and with no time limit. If they're taken, the next car park is 120 m further along Mason Street, away from the centre.

Public transport

The nearest bus stop is 200 metres towards the centre; from there, walk straight along Mason Street. It's about 12 minutes from the bus and train station.

By car from the motorway

It's 4 km from the M6 junction. At the junction with Brick Lane, turn right; the office is the second building on the left, with a dark façade and an ochre stripe.

Step-free access

The entrance on Mason Street is step-free, and the meeting room is on the ground floor. If you need help getting in, give us a call before you arrive.

Where we work and travel to site
Town or villageDistanceTravel to site
Galway city and suburbsup to 8 kmincluded in the price
Oranmore15 kmincluded in the price
Athenry22 kmincluded in the price
Oughterard24 kmincluded in the price
Tuam30 kmincluded in the price
Loughrea34 kmincluded in the price
Other places beyond 60 kmover 60 km€0.95/km, only for jobs over €60,000
14 — Questions

FAQ

The questions we're asked most often. If yours isn't here, put it in the form.

Is the calculator price final?

No, it's a guide. It's there so you know whether your plans fit your budget at all. The final price comes from the itemised estimate after the site visit, with the actual quantities, materials and site conditions. The difference between the calculator and the estimate is usually under 15%.

How do I send an enquiry when there's no email address on the site?

Use the form in the Contact section. Your message reaches the company inbox just like an email, and we reply within 24 hours. If it's urgent, call us during office hours.

Do you take on smaller jobs, not just whole houses?

Yes. The smallest job we take on is about €3,000 excluding VAT — a bathroom renovation or new floors in an apartment, for example. For smaller work we charge the hourly rate from the price list.

Do I need drawings before the site visit?

No. For renovations, it's enough for us to come and measure what's there. For a new build we need drawings, but we can arrange them through the architectural designer we work with, including planning permission.

Do you buy the materials, or do I?

Normally we supply the materials, and you'll see each one named and priced in the estimate. If you'd like to buy some items yourself — typically tiles, sanitaryware or flooring — that's fine, but they need to be on site before that stage starts, or the date moves.

Can I live in the apartment during the renovation?

For a complete renovation we don't recommend it — for the first three weeks the apartment has no water and there's dusty demolition work. For a partial renovation of one room or the bathroom you can stay; we seal the area off with a dust screen and only turn the water off at agreed times.

How do you deal with dust, noise and neighbours in an apartment block?

We only do noisy work on weekdays between 8:00 and 17:00, never at weekends. We cover the common areas with sheeting and clean the corridor every day. Before work starts, we put up a notice for the neighbours with the dates and the site manager's contact details.

What if something unexpected turns up during the strip-out?

A rotten joist, for example, a cracked lintel or aluminium wiring. We stop work at that spot, record what we've found, propose a solution and put the price on a variation order. We only carry on once you've signed it, so the invoice holds no surprises.

Can a site visit be arranged outside working hours?

We do site visits from 7:00 to 18:00, including early evenings. On Saturdays we'll come by arrangement, if nothing else works. Sunday is our day off, and our sites don't run.

How far from Galway do you go?

Usually up to 60 km, which covers Galway, Athenry, Oughterard, Loughrea, Oranmore and Tuam. We only go further for larger jobs over €60,000, and travel is then charged as per the price list.

15 — Contact

Request a quote

Tell us what you need built or renovated. We'll get back to you within 24 hours and arrange a site visit.

Your message goes to the KVADER inbox. We reply within 24 hours, usually within a few hours on working days. If you need an answer straight away, call us.

Phone

your number here

Call during office hours. Outside them, use the form and we'll get back to you the next working day.

Office

KVADER — building contractors
26 Mason Street
Galway

The meeting room is on the ground floor, with the entrance on Mason Street. There are 6 free parking spaces outside.

Opening hours

Monday — Thursday7:30 — 16:00
Friday7:30 — 14:00
Saturdayby arrangement
Sundayclosed
Site visits7:00 — 18:00

About this example

Like this website?

This website is an example from my portfolio. KVADER and all its details are made up — they're only here to show what a finished website for a building company can look like, with a price list, a calculator, a schedule and an enquiry form.

This example was designed and programmed by Alex Poliak. I'll build a website for your company the same way — with your content, prices and photos of your projects.

Custom websites from €250. First design within 3 days. Free, no-obligation consultation.

Visit apoliak.online your number here

Contact the author